Production Cycle Optimization - How to Reduce Injection Time 2025
Practical techniques for reducing cycle time on Tederic injection molding machines by 10-30% without quality compromises. Cooling optimization, injection speed profiling, case study: 45→32 sec.
TEDESolutions
Expert Team
Introduction - the value of every second
Injection molding cycle time is the most important economic parameter in mass production. Reducing the cycle by just 5 seconds when producing 3 million parts annually means saving 4,167 machine hours – equivalent to €50,000-€125,000 in annual savings.
In Polish injection molding industry, average cycle times are 28-45 seconds for automotive parts and 15-30 seconds for packaging. Studies show that in 60-75% of cases this time can be reduced by 10-30% without quality compromises.
Why is cycle optimization critical?
- Production costs: Shorter cycle = more parts per hour = lower unit cost
- Capacity: 20% cycle reduction = 25% productivity increase without new machines
- ROI: Optimization investment (€10-30K) pays back in 3-12 months
- Competitiveness: Shorter cycle time = lower quote price = more contracts
Key insight: In a typical injection molding cycle, cooling accounts for 50-70% of total time. This is the biggest savings potential.
Anatomy of the injection molding cycle
To effectively optimize cycle time, it's necessary to understand what phases it consists of and where the biggest savings potential lies.
5 main phases of the injection molding cycle
| Phase | Time [s] | % of cycle | Reduction potential |
|---|---|---|---|
| Mold closing | 2.8 | 8% | Low-medium (5-15%) |
| Injection + filling | 1.2 | 3% | Medium (10-30%) |
| Packing/holding | 8.5 | 24% | High (20-40%) |
| Cooling | 22.0 | 62% | VERY HIGH (20-50%) |
| Opening + ejection | 3.5 | 10% | Medium (10-20%) |
Conclusion: Cooling is 62% of the cycle – the first area for optimization. Even a 27% cooling time reduction translates to 25% total cycle reduction.
Cooling optimization (50-70% of cycle)
Cooling is the biggest time consumer in the injection molding cycle and simultaneously the area with the greatest optimization potential.
1. Mold temperature optimization
Problem: Higher mold temperature = better filling, but longer cooling. Lower temperature = shorter cooling, but risk of short shots.
Solution: Find the minimal acceptable mold temperature (MAMT)
DOE Method:
- Set baseline mold temp (e.g. 50°C for PP)
- Run series with temperatures: 45°C, 40°C, 35°C
- Monitor: cooling time, surface quality, filling, dimensional stability
- Select lowest temperature meeting all quality requirements
Example: Reducing mold temp from 50°C to 40°C (PP)
- Cooling time reduction: 18s → 14s (-22%)
- Annual savings: 3.3M parts × 4s × €0.05/min = €11,000
2. Conformal Cooling - mold cooling revolution
Traditional cooling channels are straight, drilled. Conformal cooling uses 3D printing to create channels that follow the cavity shape, ensuring uniform cooling.
Benefits:
- 20-40% cooling time reduction
- Uniform cooling → less warpage
- Ability to cool difficult geometries
- Higher surface quality
Challenges:
- Cost: €15,000-€80,000 additional for mold
- Break-even: Typically 300,000-1,500,000 parts
ROI example:
- Investment: €35,000
- Cycle time reduction: 42s → 32s (-24%)
- Annual production: 800,000 parts
- Savings value: €100,000/year
- Payback period: 4.2 months ✅
3. Precise temperature control - TCU ±0.5°C
Standard temperature control units (TCU) have accuracy of ±2-3°C. Premium TCU achieve ±0.5°C.
Benefits:
- More repeatable solidification time
- Can reduce cooling time closer to minimum without variability risk
- Typical savings: 3-8% of cycle time
Cost: €8,000-€18,000 | ROI: 12-24 months for high-volume production
4. Hot runner systems
Cold runner: Runner must cool before ejection → additional 3-8 seconds
Hot runner: No runner to cool → immediate elimination of 3-8s from cycle
For high-volume applications (>500K parts/year) hot runner is a game changer. See details in hot runner economics section.
Injection and holding optimization
Multi-stage injection profiling
Instead of constant injection speed, use 2-5 stage profile:
| Stage | Position [mm] | Speed [mm/s] | Goal |
|---|---|---|---|
| 1 | 0-15 | 60 | Gentle start (no jetting) |
| 2 | 15-85 | 180 | Maximum filling speed |
| 3 | 85-100 | 90 | Gentle finish |
Benefits: Shorter fill time (1.8s → 1.3s, -28%), better quality, more uniform packing.
Gate freeze detection - critical technique
Problem: Holding time is often set "for safety" - 2-5 seconds longer than actually needed.
Gate freeze study method:
- Set holding time definitely too long (e.g. 15s)
- Run series with holding time: 12s, 10s, 8s, 6s, 4s, 2s, 0s
- Weigh 10 parts from each series
- Gate freeze time = point where further holding time increase does NOT increase part weight
- Set production holding time = gate freeze + 0.5-1.0s (safety margin)
Typical savings: 2-5 seconds at zero investment – always the first optimization step!
Hot runner vs cold runner - economics
System comparison
COLD RUNNER:
- Material flows through cold sprue and runner
- Runner must cool → additional 3-8s cooling time
- Wasted material (runner = 15-40% shot weight)
- Lower mold cost (€30K-€80K cheaper)
HOT RUNNER:
- Heated manifold maintains material molten
- Elimination of 3-8s runner cooling time
- Zero material waste
- Higher initial cost: €20,000-€150,000
ROI calculation example - automotive part 180g PA6, 2-cavity mold
| Parameter | Cold runner | Hot runner |
|---|---|---|
| Mold cost | €85,000 | €133,000 |
| Cycle time | 38 seconds | 33 seconds (-13%) |
| Material waste | 20.9% | 0% |
| Parts/year (3-shift) | 1,661,000 | 1,912,000 (+15%) |
| Annual savings | - | €66,900 |
Payback period: €48,000 / €66,900 = 8.6 months ✅
Recommendations:
- Hot runner recommended: Production >500K parts/year, long runs, expensive materials
- Cold runner acceptable: Low volumes (<200K/year), frequent material/color changes
Case study - reduction from 45→32 seconds
Real cycle time optimization case study conducted by TEDESolutions for a Polish tier-1 automotive manufacturer.
Project profile
- Part: Center console cover, ABS+PC, 285g
- Machine: Tederic NEO.H260
- Annual production: 420,000 pieces (2-shift)
- Baseline cycle time: 45 seconds
3-month optimization program
Phase 1: Low-hanging fruit (Week 2-3, €0 investment)
- Mold temp reduction: 65°C → 60°C → -2.5s cooling
- Gate freeze study → -3.3s holding
- Faster mold close/open speeds → -0.7s
- Result: 45.0s → 38.5s (-14%)
Phase 2: Process profiling (Week 4-6, €0-€5K)
- 3-stage injection profile → -0.3s
- Holding pressure decay profile → -1.2s
- Aggressive cooling cut → -1.7s
- Result: 38.5s → 35.3s (-8%)
Phase 3: Equipment upgrade (Week 7-12, €22,300)
- Premium TCU ±0.5°C (€9,800) → -1.8s
- Cooling channel upgrade (€12,500) → -1.5s
- Result: 35.3s → 32.0s (-9%)
Final results
| Parameter | Start | End | Improvement |
|---|---|---|---|
| Cycle Time | 45.0s | 32.0s | -28.9% |
| Parts/hour | 80 | 112.5 | +40.6% |
| Cpk (dimensional) | 1.28 | 1.52 | +18.8% |
| Scrap rate | 2.8% | 1.2% | -57% |
ROI:
- Total investment: €37,300 (€22,300 equipment + €15,000 consulting)
- Annual benefits: €70,780/year (increased capacity, reduced scrap, energy)
- Payback period: 6.4 months ✅
Key takeaways
- Low-hanging fruit most important: Phase 1 (zero investment) delivered 14% reduction
- Gate freeze study critical: 3.3s saved just through proper holding time
- Cooling dominates: 67% of total reduction came from cooling optimization
- Quality improved: Aggressive optimization did NOT degrade quality - opposite (Cpk +18%)
Troubleshooting and pitfalls
Cycle time optimization is a balance between speed and quality. Here are the most common problems:
Problem 1: Warpage after cooling reduction
Cause: Part didn't solidify sufficiently - internal stress causes deformation.
Solution:
- Step back: increase cooling time by 2s
- Reduce cooling in 1s steps, test 50 parts after each change
- Measure parts immediately and after 24h - compare
- Consider cooling jig for hot parts
Problem 2: Sink marks after holding reduction
Cause: Insufficient packing - gate froze too early.
Solution:
- Increase holding pressure: +50-100 bar
- Optimize switchover: earlier injection→holding transition
- Long-term: redesign part for uniform wall thickness
Problem 3: Flash after injection speed increase
Cause: High dynamic pressure opens mold during injection.
Solution:
- Increase clamp force: +10-15%
- Multi-stage injection: slower speed at end of fill
- Check mold maintenance: parallelism, wear, sealing surfaces
Golden rule of optimization
"Optimize aggressively, but validate rigorously"
- Each change: test minimum 50-100 parts
- Measure dimensional, visual, functional quality
- Monitor Cpk - don't accept drop >10%
- If in doubt → step back and re-assess
Summary and roadmap
Key conclusions
1. Cycle time is the most important economic parameter
Reduction by 5 seconds at 3M parts/year = €50K-€125K annual savings. In most cases 10-30% reduction is achievable without quality compromises.
2. Cooling is the biggest potential (50-70% of cycle)
- Mold temperature optimization (DOE study)
- Conformal cooling (20-40% reduction, ROI 4-12 months)
- Premium TCU ±0.5°C (3-8% variability reduction)
3. Holding time optimization - low-hanging fruit
Gate freeze study can save 2-5 seconds at zero investment.
4. Hot runner = game changer for high volume
Elimination of 3-8s + zero waste. Payback <12 months for >500K parts/year.
5. Moldflow simulation = fastest route to optimum
Investment €5K-€15K, return €60K-€200K+. ROI often <1 month for new molds.
Optimization roadmap - Step by step
PHASE 1: Low-cost optimization (0-2 weeks, €0)
- Gate freeze study → optimal holding time
- Mold temp DOE → find MAMT
- Faster dry cycle speeds
- Target: 8-15% reduction
PHASE 2: Process profiling (2-4 weeks, €0-€5K)
- Multi-stage injection profiling
- Holding pressure decay profile
- Aggressive cooling time cut (quality monitoring)
- Target: 5-12% additional reduction
PHASE 3: Equipment upgrades (2-6 months, €10K-€80K)
- Premium TCU ±0.5°C (€8K-€18K)
- Cooling channel modifications (€5K-€25K)
- Conformal cooling (€15K-€80K) - new molds, high volume
- Hot runner (€20K-€150K) - for >500K parts/year
- Target: 10-25% additional reduction
TOTAL POTENTIAL: 23-52% cycle time reduction
Tederic machine capabilities
NEO Series (hydraulic): Mold close speed up to 280 mm/s, repeatability <0.5%, responsive hydraulics for multi-stage profiles
DREAM Series (electric): Ultra-fast cycles (400 mm/s), repeatability <0.3%, 30-50% lower energy consumption, precise temperature control ±1°C
Typical ROI for different optimizations
| Optimization type | Investment | Cycle reduction | Payback |
|---|---|---|---|
| Process only (Phase 1-2) | €0-€5K | 10-20% | Immediate |
| Premium TCU | €10K-€18K | 3-8% | 4-14 months |
| Conformal cooling | €15K-€80K | 15-30% | 4-18 months |
| Hot runner | €25K-€150K | 10-25% | 6-24 months |
Best practices - checklist
✅ Planning
- Start with cycle breakdown analysis - where is the time?
- Set clear, realistic targets (10-30%)
- Prioritize cooling optimization
✅ Execution
- Incremental changes - not everything at once
- Validate rigorously - minimum 50-100 parts
- Monitor Cpk - don't accept degradation
- Document everything
✅ Investment decisions
- Calculate ROI properly - include capacity increase value
- Hot runner - strongly consider for >500K parts/year
- Conformal cooling - evaluate for new high-volume tools
Need support in choosing an injection molding machine?
Contact our TEDESolutions experts and find the perfect solution for your production
Related articles
Discover more valuable content
Production Cycle Optimization - How to Reduce Injection Time 2025
Practical techniques for reducing cycle time on Tederic injection molding machines by 10-30% without quality compromises. Cooling optimization, injection speed profiling, case study: 45→32 sec.
Injection Molding Defects - Identification, Causes and Solutions 2025
Guide to the 6 most common injection molding defects. Causes, solutions with Tederic parameters, case study of 82% scrap reduction. Achieve world-class quality.
Standards and Compliance in Injection Molding - Audit Guide 2025
Comprehensive guide to ISO 9001, IATF 16949, ISO 13485, and CSRD standards for injection molding facilities. Learn how to prepare production for audits and certification.
